Jul 2019 - project progress
"Yi Xin Qiao" of Liangqiao Village was successfully built at the end of July. It is 2 meters wide, 11.8 meters long and 3.5 meters high.
Mar 2019 - project progress
Main structure work of the bamboo bridge was almost completed. Once the site foundation work is done, the bridge will be transported to the site for installation.
Mar 2018 - 1st Investigation
The team conducted the 1st investigation trip in March and initially proposed to build a 10-meter bamboo footbridge for the villagers. |